Built to Evolve: Four Decades of Controls at Bell Works

October 9, 2026

Most building automation projects have a fairly clear beginning and end. A need is identified, a control system is designed and installed, the project is commissioned, and the building moves on to the next capital improvement. At Bell Works in Holmdel, New Jersey, the story has unfolded a little differently.

Engineered Energy Solutions (EES) first worked at the sprawling former Bell Labs research facility in the 1980s, installing controls designed to reduce the enormous campus’s energy consumption. Nearly four decades later, EES is still working in the same building. But very little else is the same.

The former Bell Labs complex has been transformed into Bell Works, a mixed-use “metroburb” encompassing offices, retail, dining, entertainment and other uses. Along the way, the control technology has evolved from PLCs and loop controllers to a modern building management system (BMS) supporting a facility that continues to change.

Through it all, the controls philosophy has increasingly become one of flexibility: make standard connections easy, retain the ability to engineer more sophisticated solutions when necessary, and avoid making today’s controls decisions an unnecessary limitation on tomorrow’s building.

A Second Beginning

When EES first worked at the facility, it was still Bell Labs. The energy-control project ultimately saved Bell Labs approximately $500,000 per year and paid for itself in less than two years.

The facility’s fortunes changed dramatically in the decades that followed. Bell Labs eventually left, the property sat largely vacant, and Somerset Development acquired the approximately 2-million-square-foot complex with plans to reinvent it. That ultimately led Somerset back to EES.

The new owners found the EES name on HVAC equipment throughout the facility and contacted the company, where some of the institutional knowledge from the original project still remained. One EES engineer who recently retired after 38 years with the company had worked on Bell Labs as his first project.

Even more remarkable, portions of the old controls infrastructure were still operating. An old DOS-based computer was still running when EES returned to the site. EES was eventually able to restore roughly 80 percent of the decades-old control system, providing Somerset with a functioning foundation as redevelopment moved forward.

Beginning around 2016, EES started what would become a multiphase modernization of the building controls. Rather than replacing everything at once, the system evolved through a series of projects and major capital investments.

Today, EES controls systems including chillers, pumps, cooling towers, air handlers, variable air volume (VAV) equipment, variable refrigerant flow (VRF) systems and an expanding collection of tenant equipment.

Built for Different Technologies and Future Change

A building of Bell Works’ size and age does not contain equipment from one generation or manufacturer. Controllers and packaged equipment from ABB, Carrier, Trane and others coexist with PLC-based controls and technologies installed at different points in the building’s history.

EES built the supervisory system around the Tridium Niagara platform, using controllers distributed throughout the building to connect the various underlying systems and communication protocols. The BMS brings those systems together through a common interface where operators can navigate the building by location, examine equipment status, and view trends and historical information. That architecture becomes particularly valuable as the building continues to change.

New tenants utilize approved engineers who determine the HVAC and controls requirements for their spaces. EES then provides the supervisory integration needed to bring those systems into the larger building environment. The objective is not to require every new piece of equipment to come from the same manufacturer. It is to provide an architecture capable of accommodating different equipment as the building evolves.

Modern building automation platforms provide standardized methods for integrating many common controllers, equipment types and communication protocols. When those capabilities meet the application’s needs, EES can take advantage of them without unnecessarily creating a custom solution.

But not every operating requirement arrives neatly packaged with the equipment. One example at Bell Works involved VRF equipment, which can efficiently serve multiple building zones and, in some applications, put energy from one area to productive use elsewhere. The equipment being integrated at Bell Works did not natively provide the night-setback functionality the facility wanted. Rather than accepting that limitation, EES developed additional control logic to provide the desired operating strategy.

That combination is important: straightforward integration for routine applications, coupled with the ability to engineer more sophisticated solutions when the application requires them. It also provides future flexibility for the building owner. An open architecture can reduce the likelihood that the existing BMS dictates future equipment choices. When a chiller, air handler, VRF system or other piece of equipment needs to be added or replaced, the owner can focus first on selecting equipment appropriate for the application, then determine the best way to integrate it into the larger building system.

Learning From the Building

As the BMS has grown, it has also accumulated years of operating history. Historical data allows EES and Bell Works personnel to look beyond current conditions and examine how equipment and spaces have performed over time. Trends can help answer questions about settings, operating strategies and how particular areas of the building behave under different conditions.

In that sense, the controls system has developed an institutional memory of the building, providing information that can guide future decisions even as equipment, tenants and personnel change.

From Controls Contractor to Onsite Resource

The EES relationship has evolved along with the controls. What began with restoration and modernization of the central building systems expanded into tenant fit-outs, networking, incremental controls projects and continuing modernization throughout the facility.

Eventually, the volume and continuity of that work made having EES expertise onsite valuable. For approximately four years, an EES engineer has been embedded at Bell Works as an extension of the facility team. The role reflects the pace of change at the property. New tenant spaces continually need to be incorporated into the building systems, existing areas are modernized, and smaller controls projects arise between major capital improvements. Having an engineer onsite who already understands the BMS architecture and the facility allows those efforts to move forward efficiently. That presence also provides ready access to EES expertise for troubleshooting and support when operational issues arise.

The arrangement represents something considerably different from the traditional model in which an integrator completes a project and returns only when another project is awarded. EES has become an ongoing technical resource supporting the continued evolution of Bell Works.

Building for the Next Change

The Bell Works story is unusual partly because of its duration. Few integrators get the opportunity to return to the same facility nearly 40 years after their original project and participate in reinventing it for an entirely different purpose.

But longevity may not be the most important lesson. The building continues to change. New tenants arrive, spaces are reconfigured, equipment is replaced and new technologies become available. Major capital projects take place alongside smaller improvements. The goal is not to predict all of those changes in advance. It is to create enough flexibility that each one does not require starting over.

Nearly four decades after EES first began controlling energy at Bell Labs, the controls system is no longer simply managing the building as it exists today. It is providing a foundation for whatever Bell Works becomes next.

← Back to News
Engineered Energy Solutions
291 US Hwy 22, Building 5, Suite 42
Lebanon,
NJ
08833
info@ees-inc.com (908) 252-3800
© 2026 Engineered Energy Solutions. All Rights Reserved.
Website by Luminus